window.dataLayer = window.dataLayer || []; function gtag(){dataLayer.push(arguments);} gtag('js', new Date()); gtag('config', 'G-QSHV8B6GLM');

Project Broadland Substation

Client: Basin Electric Power Cooperative

Location: Huron, SD

Completion Date: November 2018

Scope/Description:

  • Complete removal of existing concrete piers and reinstall helical anchors.
  • 230 KV and 345 KV Electrical equipment were removed and reinstalled after helical anchors were completed.
  • Equipment consisted of circuit switchers, CCVT’s, MOD’s, three-phase disconnects, and LA’s.