Twin City to N. Stanwood 15kV Re-Conductor

Client: Snohomish County PUD

Location: Stanwood, WA

Completion Date: Ongoing Contract

Scope/Description:

  • Provided all labor, equipment and material to rebuild approximately 1.25 miles of 115kV line
  • Added 12kV double circuit distribution under-build between the future Twin City Substation site and North Stanwood Substation