Ashton to St. Anthony 45kV RE-frame and Static

Client: Rocky Mountain Power

Location: Casper, WY

Length: 15 miles

Completion Date: Fall 2019

Scope/Description:

  • 46kV rebuild – structure and OHSW replacement
  • Tangent wood poles
  • 3/8” OHSW
  • High water and swampy ground conditions

Highlight: FB Titan paused work in the spring to accommodate the client’s outage schedule, farming, and irrigation requirement.