Goodwin Bridge 115kV

Client: Chelan County PUD

Location: Cashmere, WA

Completion Date: October 2020

Scope/Description:

  • Relocation and Replacement of 115kV line to including everything from:
    • constructing access
    • installation of concrete foundations
    • excavation of direct embed steel poles
    • transfer and sag existing Andrew York
  • Anderson Canyon 3 Line, stringing and sag Mission Substation Tap Line and demolition of existing lines.
  • The project also contains relocation and structure replacement of a 12.47kV Distribution line, to include a portion of underground duct and vault system installation.